Four Phase Project Restores Site, Wetlands, Stream, and Wooded Area
Auxier and ENTACT were engaged to perform a four-phased remedial action project to support the decommissioning of this former glass and super alloy additives manufacturing facility.
Due to historical and metallurgical operations conducted at the site, metals and radiological impacts were present in soil and sediment on the property and off-site, consisting of wetlands, a stream channel, and wooded upland areas. Phase 1 of the project addressed the impacted materials on the property limits, and Phases 2, 3, and 4 addressed the impacted materials that had migrated off-site and required remediation.
Phases 1 and 2 scopes entailed the excavation of 12-inches from the stream channel and 6-inches from the adjacent banks and floodplain for a total removal of 6,540 cubic yards over a 7-acre portion of the site.
Project Scope of Work
- Onsite material transport, handling, storage, conditioning, and loadout
- Importation and placement of approximately 4,940 cubic yards of select fill and approximately 1,600 cubic yards of highly organic select fill meeting site-specific sediment Ecological Screening Values
- Installation and operation of an active stream bypass
- Construction water dewatering, treatment, and discharge
- Restoration of wetlands with plantings, seed, and mulch
- Installation of a 1-acre asphalt cap
Phases 3 and 4 were similar in scope with a total removal of 3,960 cubic yards over a 6-acre area, which included importation and placement of approximately 1,305 cubic yards of select fill and approximately 2,655 cubic yards of highly organic select fill.
Ancillary Support Scope of Work
- Surveying and maintaining site controls
- Procurement of local permits
- Air monitoring
- Dust control
- Installation, maintenance, and removal of soil erosion and sediment controls, and site access road construction and improvements
Innovative Remediation Strategies Achieves Client’s Goals and Cost Savings Auxier decommissioned, decontaminated, and demolished a former rare earth minerals processing plant in a larger chemical manufacturing complex. The site was approved for […]
Multi-Phase Remediation and Restoration Creates Pond, Wetlands, and Walking Trails Auxier and ENTACT are performing an ecological restoration of 100+ acres previously home to several chemical manufacturers, a clay mining operation, and […]
Former Mine Site Restoration Completed Ahead of Schedule with an Emphasis on Worker Safety ENTACT conducted three remedial actions at a former copper mine site in Nevada. The remediation required the removal […]